Guadalupe County / Cibolo /

Legacy San Antonio (1000 Bolton Road)

Approved · not yet builtLegacy Investing · Record updated 2026-11-27

Draft record. This page has not yet been checked line by line against the source documents. Treat it as a lead, not a citation.

Legacy Investing, a real estate firm based in Arlington, Virginia, plans a single 242,640-square-foot, 50-megawatt data center on the 39-acre former San Antonio Karting Complex at 1000 Bolton Road in Cibolo; the company has said the site could grow to 150 megawatts. City staff approved the site plan administratively in April 2026 and a revised plan in August 2026 because the land has been zoned light industrial since 2016, so there was no public hearing or council vote, and the city says it gave no incentives. A city report lists a permit issued for the project on September 16, 2026; no dated report of construction on the site was found. As of late November 2026 the council had discussed but not adopted data center rules or a moratorium.

Where this stands and what you can do

Local approvals are on record, but construction has not been reported. Terms already signed are hard to reopen. What is still open is anything not yet voted on: later phases, tax abatements, utility and road agreements, and state permits.

  1. Find out what is still to be decided. Ask the city or county which approvals remain: annexation, a tax abatement, utility service, plats, road agreements. Each one is a vote where terms can be added.

    Contact: Cibolo City Council

    A letter you can copy: ask for conditions before a vote

    Send to: Mayor and council members. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Legacy San Antonio (1000 Bolton Road) - conditions before any vote
    
    Dear Mayor and Council Members,
    
    I live in [neighborhood / street] and I am writing about Legacy San Antonio (1000 Bolton Road) (Legacy Investing).
    
    I am not asking you to turn away investment. I am asking that no annexation, zoning change, utility agreement or tax abatement for this project be approved until the following are written into the ordinance or the agreement itself:
    
    1. Water: a cap on annual water use, stated in acre-feet, with a yearly public report of actual use.
    2. Noise: a limit measured at the property line, and set hours for testing backup generators.
    3. Distance: a minimum setback and a buffer between the buildings, the generators and the nearest homes.
    4. Power: disclosure of any on-site power plant or generators, and the air permits they will need.
    5. Money: any tax abatement tied to a minimum investment, a jobs and wage floor, and a clawback if those are missed.
    6. Transparency: the draft agreement posted publicly at least [14] days before the vote.
    
    Please tell me which of these the current draft includes, and when the public will be able to read it.
    
    Thank you,
    [Name]
    [Address]
    [Phone or email]
  2. Speak or write on any tax abatement not yet granted. If no abatement has been approved, it can still be denied or conditioned.

    Contact: Guadalupe County Commissioners Court

    A letter you can copy: comment on a tax abatement

    Send to: The body considering the abatement (city council or commissioners court). Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Tax abatement for Legacy San Antonio (1000 Bolton Road)
    
    Dear [Mayor and Council Members / Judge and Commissioners],
    
    I am writing about the tax abatement requested for Legacy San Antonio (1000 Bolton Road) (Legacy Investing).
    
    A tax abatement is your decision to make; state law does not require one. Before you vote, I ask that you:
    
    1. State publicly the percentage, the number of years, and the dollar value of the taxes that would be forgiven.
    2. Compare the request with what other Texas cities and counties have granted for similar projects.
    3. Require a minimum investment, a minimum number of full-time jobs at a stated wage, and repayment if those terms are not met.
    4. Require an annual compliance report, posted publicly.
    5. Explain what Cibolo and Guadalupe County receive in return, and when.
    
    If these terms cannot be met, I ask that you vote no.
    
    Thank you,
    [Name]
    [Address]
  3. Comment on state permits. Air authorizations for generators and on-site power are often filed after local approval.

    Contact: TCEQ: comment on a pending permit · TCEQ: environmental complaint

  4. Ask for the signed agreements. Once signed, they are public records. Read what was promised.

    Contact: How to file a public information request

  5. Ask the state for rules that apply everywhere. Statewide standards on siting, water reporting and backup power are set by the Legislature.

    Contact: Who Represents Me (Texas Legislature) · Office of the Texas Governor

    A letter you can copy: write to your state senator and representative

    Send to: Your Texas state senator and state representative. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Data center siting and reporting standards - Guadalupe County
    
    Dear [Senator / Representative] [Name],
    
    I am your constituent in Guadalupe County, where Legacy San Antonio (1000 Bolton Road) (Legacy Investing) is [proposed / being built / operating] near homes.
    
    I support data centers being built in Texas. My concern is where and how fast. Outside city limits, counties have almost no say, and neighbors learn the terms after the vote. I ask that you support legislation that would:
    
    1. Give counties authority to set reasonable siting standards for large data centers: setbacks from homes and schools, noise limits, and limits on on-site power generation near neighborhoods.
    2. Require data centers above a set size to report their water and electricity use each year, publicly.
    3. Require that tax abatement and development agreements with data centers be posted before the vote, not after.
    4. Require air permits and pollution controls to be in place before on-site turbines and generators run.
    
    Please tell me your position on these, and whether a bill addressing them is filed or planned.
    
    Thank you,
    [Name]
    [Address - so your office can confirm I am a constituent]

This is general information about how local and state decisions get made, not legal advice.Who decides what, and every contact and letter in one place.

Legal entities
1000 Bolton Rd Owner, LLC; Legacy Investing
Also known as
Legacy San Antonio; Legacy Data Center SAT-1; SAT1; 1000 Bolton Road data center; Warehouse with server storage @ 1000 Bolton Rd; Ocotillo/Marion Industrial Entitlements; Skloss Commercial, Lot 1 Block 1; PZ-2026-2-SP; PZ-2026-3-SP; 1000 Bolton Rd, LLC (owner/developer named on the first site plan)
Location
1000 Bolton Road (Marion mailing address, ZIP 78124), north side of Bolton Road west of South Santa Clara Road and north of I-10; the former San Antonio Karting Complex
Jurisdiction
Inside the City of Cibolo. The tract was annexed at the owner's request by Ordinance 1172 on August 9, 2016 and zoned Light Industrial (I-1) by Ordinance 1173 on August 23, 2016. The mailing address is Marion, and Green Valley SUD's 2026 feasibility studies describe the tract as in Cibolo's ETJ.
Site
39.14 acres
Power
50 MW
Water
Sources give different figures. The City of Cibolo FAQ (2026) says the closed-loop design 'will use slightly more than 300,000 gallons per month.' The city staff deck of July 17, 2026 says 6 acre-feet to fill the cooling system once and up to 500 gallons a day afterward. Green Valley SUD's March 2026 water study, prepared for the earlier two-building layout, covers 33 equivalent dwelling units, which the district projects at 13.2 acre-feet a year; its wastewater study estimates an average 12,600 gallons a day.

Tax incentives

Granted byTermsDate
Texas Comptroller'Legacy Data Center SAT-1' is on the Comptroller's list of registered qualifying data centers, with 1000 Bolton Rd Owner, LLC as owner, occupant and operator (registration DC345668). Registration is the state program that exempts certain purchases by qualifying data centers from state sales and use tax; the list does not give an exemption end date or a dollar value. The City of Cibolo states it granted no abatement, Chapter 380 agreement, grant or other local incentive.2026-09-14

Documents and sources

89 items: Government records (48) · Meetings (29) · News and company statements (12)

Government records

Ordinances, resolutions, agreements, notices, permits and filings.

DateDocumentFromLink
2026-10-19Summary: Data Center Permits Issued by TCEQ After 9/21/2026
Advocacy group's list. States that on October 13 TCEQ issued a construction stormwater permit to Sitespan, LLC for 'San Antonio Karting Complex located at 1000 Bolton Road, Marion TX.'
Public CitizenOpen
2026-10-13TCEQ construction stormwater general permit coverage TXR1564ZS, 'SAT1'
Held by Sitespan, LLC of Lenexa, Kansas (CN606572139) as operator since 10/13/2026, not by Legacy Investing. Status shown as Active on 2026-11-27. Texas Public Radio reported on October 22, 2026 that TCEQ said a permit issued October 13 to Sitespan for a Bolton Road data center project had been suspended after the governor's September 21 directive; the registry page does not show a suspension.
Texas Commission on Environmental QualityOpen
2026-10-01Economic Development report, October 2026
Lists 'Legacy San Antonio Data Center - 1000 Bolton - (Permit issued 9.16.26)'. The report does not say which permit or whether work has begun.
City of CiboloOpen
2026-09-14Registered Qualifying Data Center Projects list: 'Legacy Data Center SAT-1'
Checked 2026-11-27. Entry 'Legacy Data Center SAT-1', effective date 09/14/2026, with 1000 Bolton Rd Owner, LLC as owner (DC345668-OW1), occupant (DC345668-OC1) and operator (DC345668-OP1). The list has no address column; the match rests on the project and entity names.
Texas ComptrollerOpen
2026-09-01Economic Development report, September 2026
Lists 'Legacy San Antonio Data Center - 1000 Bolton Rd (Commercial Shell Building & Concrete)' in the building permit section.
City of CiboloOpen
2026-09-01TCEQ construction stormwater general permit coverage TXR1501ZI, Legacy San Antonio
Held by Legacy Investing (CN606556132) as operator since 09/01/2026. Status shown as Active on 2026-11-27. No complaints, investigations or enforcement listed.
Texas Commission on Environmental QualityOpen
2026-08-27Revised site plan PZ-2026-3-SP, 'Legacy San Antonio' civil construction plans, stamped and approved
47 sheets, the civil and landscape sheets by Kimley-Horn with a cover dated July 16, 2026, stamped 'Reviewed for compliance' and signed 8/27/26. Owner/developer shown as Legacy Investing, Arlington, Virginia. Site data table: Skloss Commercial Lot 1 Block 1 (Doc. 2016008606); site acreage about 38.659; one 242,640 sq ft building, 29 ft 8 in high; about 26.6 acres impervious cover; 71 parking spaces. The city's August 2026 development report gives the approval date as 8/28/2026.
City of CiboloOpen
2026-08-24City Engineer review letter, 1000 Bolton Road (PZ-2026-3-SP)
Finds the development 'in conformance with the city of Cibolo Unified Development Code and Flood ordinances.'
Colliers Engineering & Design, as City EngineerOpen
2026-08-24Water Use in Perspective: daily and monthly averages
Follow-up table to the handout. It has no data center row.
City of CiboloOpen
2026-08-17Town hall handout, 'Putting Water Use Into Perspective'
Graphic comparing monthly water use by land use, with a closed-loop data center shown among them.
City of CiboloOpen
2026-08-17Town hall presentation slides by Overwatch
General presentation on how data centers operate. The city FAQ states Overwatch is not connected to any proposed project in Cibolo and was not paid.
Overwatch, posted by the City of CiboloOpen
2026-08-01Economic Development report, August 2026
Lists 'Revised Site Plan Approved 8/28/2026' and 'Legacy San Antonio Data Center - 1000 Bolton Rd - Commercial concrete permit issued for Building Phase 1, under plan review'.
City of CiboloOpen
2026-07-20City Council Ordinance Subcommittee meeting
No agenda or minutes found. The July 28 staff report says the subcommittee met July 20 and recommended that council consider the approval process (by right or conditional use permit) and standards for water, energy, pollution and noise.
City of CiboloNot yet archived. Have it?
2026-07-17City staff slide deck, 'Data Center Entitlements and Resources'
51 slides attached to the July 28, 2026 council item. Timeline slide: April 6 application, April 29 site plan approved, May 18 application to revise, 'No permits approved at this time.' Electric slide: the substation on Bolton Road has 100 MW capacity, 70 MW allocated to existing and proposed users and 30 MW available. Water slide: 6 acre-feet to fill the cooling system once and up to 500 gallons a day afterward; 'Package plant to be built by owner' and district sewer 'when line extended.' Read by OCR.
City of CiboloOpen
2026-07-11Petition to Relocate the Proposed Data Center Near I-10 and Bolton Road, Cibolo, Texas
Resident petition; 4,083 signatures shown when opened on 2026-11-27. Date is the creation date shown on the page.
Change.orgOpen
2026-06-15Traffic Impact Analysis worksheet, PZ-2026-3-SP
One 242.64 thousand sq ft building; 37 peak-hour trips.
Kimley-HornOpen
2026-06-01Economic Development report, April/May/June 2026
Adds 'Warehouse with server storage @ 1000 Bolton Rd - Commercial concrete permit in plan review'.
City of CiboloOpen
2026-04-28Site plan approval PZ-2026-2-SP, '1000 Bolton Rd. Site Improvements' (city-signed plan set)
17 sheets: civil and landscape sheets by Halff and three elevation sheets by GMA Architects dated February 20, 2026, whose title block reads "Legacy Investors". Owner/developer shown as 1000 Bolton Rd, LLC of San Antonio. Two buildings of 268,600 sq ft each. The city signature is dated 4/28/26 and the cover is stamped 'For site plan approval only, not released for construction.' City staff reports give the approval date as April 29, 2026.
City of CiboloOpen
2026-04-09GVEC electric capacity letter, 1000 Bolton Road Project
States GVEC is the certificated provider, 'has adequate electric capacity to serve the project, pending construction of underground distribution facilities', and that 'binding contracts are currently in place between GVEC and project developer to guarantee capacity availability.' No megawatt figure is given in the letter.
Guadalupe Valley Electric CooperativeOpen
2026-04-02Water Service Feasibility Study and transmittal, 1000 Bolton Road
Service application received March 19, 2026; memo dated March 23; transmittal dated April 2. Request of 33 equivalent dwelling units (25 industrial, 8 irrigation), projected by the district at 13.2 acre-feet a year. Concludes the district has adequate supply through its Canyon Regional Water Authority contract. Developer cost estimated at $484,604.59. Prepared for the earlier two-building layout. The study expires six months after the transmittal unless it moves to a non-standard service agreement, which goes to the district board. The study text describes the tract as in Cibolo's ETJ; the city's records show it annexed in 2016.
Green Valley Special Utility District (study by Utility Engineering Group, PLLC)Open
2026-04-02Wastewater Service Feasibility Study and transmittal, 1000 Bolton Road
Request of 42 industrial equivalent dwelling units; average flow about 12,600 gallons a day and peak wet-weather flow about 62,145 gallons a day at buildout. States service will not be available until the district's 1.25 MGD plant expansion is in service, that industrial pretreatment requirements apply, and that the developer extends 400 feet of 24-inch gravity main. Developer fee $310,755.48.
Green Valley Special Utility District (study by Utility Engineering Group, PLLC)Open
2026-03-01Economic Development report, March 2026
Lists 'Warehouse with server storage @ 1000 Bolton Rd (Site Plan Approved)'. The city FAQ says this report went to council on April 23, 2026.
City of CiboloOpen
2026-02-05Narrative of Application Request, Ocotillo/Marion Industrial Entitlements
One page. Describes a site plan for a 39-acre property with 'two industrial buildings that will be data centers', served by Green Valley SUD for water and sewer, with a sewer main extension submitted to the district. Gives parcel ID numbers 184790 and 161667.
Halff AssociatesOpen
2026-02-02Traffic Impact Analysis threshold worksheet, PZ-2026-2-SP
Land use 'Data Center', 540,000 sq ft, 60 peak-hour trips against 29 for the former recreational use.
HalffOpen
2025-07-08Ordinance 1497, rezoning of about 263 acres along IH-10 from Mixed-Use Regional Employment to Light Industrial
Posted by the city with the data center material. The city FAQ states 1000 Bolton Road was not part of this rezoning.
City of CiboloOpen
2025-01-10Economic Development report, January 2025 (Development Projects Update)
Lists 'Data Center @ 1000 Bolton Rd (Pre-Application)'. The city FAQ says council updates on the project began with the January/February 2025 report. The same line appears in each monthly report through February 2026.
City of CiboloOpen
2017-03-29TCEQ stormwater permit TXR15564B, San Antonio Karting Complex (expired)
Held by Skloss Development, LLC since 03/29/2017 for the kart complex that preceded the data center. Expired.
Texas Commission on Environmental QualityOpen
2016-08-23Ordinance 1173, zoning of 39.14 acres from Agricultural to Light Industrial (I-1) with a conditional use permit for a commercial go-kart complex
Adopted August 23, 2016. Recites a Planning and Zoning Commission hearing on July 13, 2016 and a council hearing on July 26, 2016. The conditional use permit conditions cover the kart track's hours and lighting.
City of CiboloOpen
2016-08-09Ordinance 1172, voluntary annexation of about 48 acres north of Bolton Road and east of Stolte Road
Passed and approved August 9, 2016. Recites public hearings on July 12 and 13, 2016.
City of CiboloOpen
Planning FAQs: Data Center FAQs, Proposed Data Center at 1000 Bolton Road, and Data Center Town Hall Q&A
Names Legacy Investing as developer. States a single 242,640 sq ft, 50 MW building; zoning unchanged since 2016; no public hearing was required; no city incentive of any kind; water from Green Valley SUD and electricity from GVEC; and that the project 'has met all applicable regulations and will be allowed to proceed if they decide to fund the project.' Gives water use as 'slightly more than 300,000 gallons per month.' The page gives the town hall date as August 18 in one place and August 17 in others.
City of CiboloOpen
Current Development Projects: Proposed Data Center at 1000 Bolton Road
Project description and the list of application documents. Lists the changes in the revised plan: two 268,600 sq ft buildings reduced to one of 242,640 sq ft; parking from 621 to 71 spaces; landscape area from 32% to 56%; 24.9 acre-feet of drainage storage. Gives building height as 27 ft 8 in; the stamped plan's site data table gives 29 ft 8 in.
City of CiboloOpen
Site plan application PZ-2026-2-SP, 'Ocotillo/Marion Industrial Entitlements'
Applicant Halff; property owner listed as Ocotillo Capital Partners of San Antonio. 39.15 acres, zoning I-1 with no change, two lots, proposed use Industrial. The city staff report of July 28, 2026 says the application was received April 6, 2026.
Halff, for the property ownerOpen
Revised site plan application PZ-2026-3-SP, '1000 Bolton Road'
Applicant SiTESPAN, LLC of Lenexa, Kansas; representative Kimley-Horn; property owner listed as Ocotillo Capital Partners. 39 acres, one lot, 243,217 sq ft, current use 'Vacant Go-Kart Track', proposed use 'Data Center'. Printed June 16, 2026; the city staff report says it was received May 18, 2026.
SiTESPAN, LLC and Kimley-Horn, for the property ownerOpen
Plat of Skloss Commercial, Lot 1 Block 1
Not obtained. The stamped site plan cites the plat as Document 2016008606 in the Official Public Records of Guadalupe County; the city staff report of July 28, 2026 describes a 'Final Plat of 1000 Bolton Road (recorded in 2018)', and an image of the plat is in the staff slide deck.
Guadalupe County ClerkNot yet archived. Have it?
Special warranty deed for 1000 Bolton Road
Not obtained. Both site plan applications list a special warranty deed among their uploaded documents, and Polsinelli announced on June 25, 2026 that Legacy Investing had acquired the site. The seller, price and recording date were not found.
Guadalupe County ClerkNot yet archived. Have it?
What's New in Cibolo: index of monthly development reports
Links every monthly report from 2024 on.
City of CiboloOpen
Public Notices and Completed Public Hearings pages
Records the August 12, 2026 Planning and Zoning hearings on the UDC amendments for unlisted uses and for data centers, the September 8 council hearing, and their outcomes. The Public Notices page lists a December 8, 2026 council hearing on adopting the 2027 Unified Development Code.
City of CiboloOpen
TCEQ Central Registry, regulated entity RN109726570 'Legacy San Antonio', 1000 Bolton Rd, Marion
Checked 2026-11-27. Three stormwater permit numbers and no air authorization are listed for this site. Customers listed as operators: Skloss Development, LLC, Legacy Investing and Sitespan LLC.
Texas Commission on Environmental QualityOpen
Franchise tax account status, 1000 Bolton Rd Owner, LLC
Delaware LLC; Texas Secretary of State registration effective 05/11/2026 (file 0806595625); registered agent Capitol Corporate Services, Inc., Austin; right to transact business Active. No officers or members are listed.
Texas ComptrollerOpen
Franchise tax account status, 1000 Bolton Road, LLC
Delaware LLC; Texas registration effective 01/30/2026 (file 0806419284); mailing address in San Antonio matching the address the site plan applications give for Ocotillo Capital Partners. The first site plan names '1000 Bolton Rd, LLC' at the same address as owner/developer.
Texas ComptrollerOpen
Franchise tax account status, Sitespan, LLC
Kansas LLC based in Lenexa, registered in Texas since 08/26/2019. Applicant on the revised site plan and holder of the October 13, 2026 stormwater coverage.
Texas ComptrollerOpen
Green Valley SUD Agenda Center: 2026 board agendas and minutes
Checked 2026-11-27. The posted 2026 board agendas (January through November) and minutes (through October 15) list non-standard service agreements by project name; none is for 1000 Bolton Road or Legacy. The October 15 minutes record a general report that the Canyon Regional Water Authority board discussed data center development.
Green Valley Special Utility DistrictOpen
GVEC board and large-load records for 1000 Bolton Road
Not found. The cooperative's capacity letter refers to binding contracts with the developer, which were not located. No board minutes were found online.
Guadalupe Valley Electric CooperativeNot yet archived. Have it?
AgendaLink meeting portal, City of Cibolo
Searched 2026-11-27. The portal's agenda item search returns no item containing the word 'moratorium', and its results for 'unlisted' show nothing after the October 19 joint workshop. The city's hearing pages show no council vote on a data center ordinance.
City of CiboloOpen
Industrial development site, 1000 Bolton Road, Marion (sale listing)
Broker listing of the kart track as a 39-acre development site with an 8-inch water main and half a mile of race track.
Matthews Real Estate Investment ServicesOpen
Legacy: San Antonio (tracker listing)
Tracker page. Says the project has four halls and that the cooperative 'can add capacity for a second building'; these statements are the tracker's and were not found in a primary record.
BaxtelOpen
1000 Bolton Road data center (Marion) (tracker listing)
Tracker entry citing the City of Cibolo application.
Texas Data Center WatchOpen
Legacy Investing Data Center (1000 Bolton Rd, Marion) (tracker listing)
Tracker page titled 'Under Construction'. The page cites no dated source for that status and says its details 'haven't yet been read back against the source.'
More Than Just ParksOpen

Meetings

Every public meeting where the project came up: agenda, minutes and recording.

DateDocumentFromLink
2026-11-30Unified Development Code Committee agenda packet
Includes the September 21 committee minutes, which note upcoming joint meetings on data centers and unlisted uses.
City of CiboloOpen
2026-10-19Joint workshop of City Council, Planning and Zoning Commission, Economic Development Corporation and UDC Advisory Committee: agenda packet
Item 6.A, 'Discussion and Possible Direction to Develop Data Center Regulations; and Develop Regulations/Administrative Procedures for UDC Unlisted Land Uses.' Staff report describes a data center zoning framework and an alternative procedure for classifying unlisted uses.
City of CiboloOpen
2026-10-19Joint workshop recording
No minutes were posted as of 2026-11-27, so the outcome is not recorded here. Timestamps not obtained.
City of CiboloWatch
2026-10-15Regular board meeting minutes, October 15, 2026
General manager reported that the CRWA Board of Managers discussed data center development, application processes, wastewater requirements and contracting, with GVEC describing the electric service process. No project is named.
Green Valley Special Utility DistrictOpen
2026-09-22City Council regular meeting, item 9.B agenda packet
Item 9.B, update on UDC amendments for data centers and setting a date for a joint meeting. 693-page packet.
City of CiboloOpen
2026-09-22City Council regular meeting, item 9.B minutes
Council discussed October 19 or 22 for the joint meeting with the UDC committee, EDC and Planning and Zoning.
City of CiboloOpen
2026-09-22City Council regular meeting, item 9.B recording
Timestamps not obtained.
City of CiboloWatch
2026-09-21Unified Development Code Committee agenda packet
Item 7.B, discussion of the proposed UDC amendments on data centers, unlisted uses and smoke shops. Includes the draft redline of data center definitions.
City of CiboloOpen
2026-09-17Economic Development Corporation meeting agenda packet
Item 9.E, discussion of the classification of new and unlisted uses in the UDC. Packet not opened; link taken from the city meeting portal.
City of CiboloOpen
2026-09-17Economic Development Corporation meeting minutes
Board discussed the unlisted-uses amendment at council's request.
City of CiboloOpen
2026-09-17Economic Development Corporation meeting recording
Timestamps not obtained.
City of CiboloWatch
2026-09-08City Council regular meeting agenda packet
Public hearing and ordinance on UDC Sec. 4.4.7, classification of new and unlisted uses. Packet not opened; link taken from the city meeting portal.
City of CiboloOpen
2026-09-08City Council regular meeting minutes
No one spoke at the hearing. Council voted 6 to 1 to send the Sec. 4.4.7 amendment to the EDC for suggestions before it returns to council.
City of CiboloOpen
2026-09-08City Council regular meeting recording
Timestamps not obtained.
City of CiboloWatch
2026-08-17Data Center Town Hall and City Council special meeting recording
Town hall at Steele High School followed by the special meeting. The city FAQ says the general managers of GVEC and Green Valley SUD answered questions near the end. Timestamps not obtained.
City of CiboloWatch
2026-08-17City Council special meeting agenda packet
Item 4.A, direction to develop regulations and definitions for data centers. Attachments: a list of possible standards (specific use permit for data centers of 75 MW or more, AI-focused or evaporative-cooled; limited-use standards for others, including noise limits, generator testing hours and proof of TCEQ authorizations) and draft UDC redlines.
City of CiboloOpen
2026-08-17City Council special meeting minutes
Three speakers and one emailed comment. Councilmembers discussed what future regulation should cover; Mayor Latimer asked the city manager to set up a joint meeting of Council, Planning and Zoning, the EDC and the UDC committee. No vote on regulations.
City of CiboloOpen
2026-08-12Planning and Zoning Commission agenda packet
Items 7.C-7.D: UDC Sec. 4.4.7, classification of new and unlisted uses. Items 7.E-7.F: UDC amendments to Sec. 1.12, 6.3, 10.2 and 13.3 'regarding Data Centers.'
City of CiboloOpen
2026-08-12Planning and Zoning Commission minutes
Sec. 4.4.7 amendment recommended for approval with added criteria, 7 to 0. On the data center amendments no one spoke at the hearing and the minutes say the item 'was tabled to a later date'; the city's hearings page says no motion was made and the amendments will return after new notice.
City of CiboloOpen
2026-08-11City Council regular meeting agenda packet
No data center action item. Packet not opened; link taken from the city meeting portal.
City of CiboloOpen
2026-08-11City Council regular meeting minutes
One speaker opposed the data center. Staff announced the town hall for August 17 at 6:30 p.m., followed by a special council meeting.
City of CiboloOpen
2026-08-11City Council regular meeting recording
Timestamps not obtained.
City of CiboloWatch
2026-07-28City Council regular meeting, item 16.F agenda packet
Item 16.F, 'Discussion/Direction concerning possible regulations for data centers' (Councilmember Patterson). The staff report gives the project history: application received April 6, 2026; site plan administratively approved April 29; revision application received May 18; up to 50 MW from GVEC; water demand equal to 33 single-family homes.
City of CiboloOpen
2026-07-28City Council regular meeting, item 16.F minutes
Six speakers in Citizens to be Heard opposed or raised concerns about the data center, and the mayor read four emails of opposition and concern. On 16.F the minutes record a staff presentation by Mr. Vasquez on the absence of incentives, the zoning procedure, coordination with Green Valley SUD, electrical use, noise and the zoning history. No vote is recorded.
City of CiboloOpen
2026-07-28City Council regular meeting, item 16.F recording
Link given in the city FAQ. Timestamp for item 16.F not obtained.
City of CiboloWatch
2026-07-14City Council regular meeting agenda packet
No data center item on the agenda; the subject came up in public comment. Packet not opened; link taken from the city meeting portal.
City of CiboloOpen
2026-07-14City Council regular meeting minutes
Five speakers in Citizens to be Heard opposed a data center in Cibolo, citing water, electricity, noise and property values; one was Guadalupe County Commissioner Germann, who asked for more transparency. Mayor Latimer said she was working with the city manager to schedule a town hall. Councilwoman Patterson requested a briefing on the data center for a future agenda.
City of CiboloOpen
2026-07-14City Council regular meeting recording
Timestamps not obtained.
City of CiboloWatch
2016 City Council agendas and minutes (annexation and zoning hearings)
Folder linked from the city FAQ for the July and August 2016 hearings on Ordinances 1172 and 1173. Individual minutes not opened.
City of CiboloOpen

News and company statements

Reporting and press releases. These are not public records; they are context and leads.

DateDocumentFromLink
2026-10-22Despite Abbott moratorium, Texas kept on issuing data center permits. Now, the state agency is shutting down its automatic filing system.
Reports the governor's September 21 directive halting TCEQ data center permits pending an ERCOT audit, a construction stormwater permit issued October 13 to Sitespan, LLC for a Bolton Road project, and TCEQ's statement that the post-directive permits 'have been suspended.'
Texas Public RadioRead
2026-09-01September Message from the GM & CEO: Data Centers, Planning Before Powering Up
General statement on loads of 75 MW or more; says any data center connecting to GVEC 'will pay 100% of all costs.' Names no project.
Guadalupe Valley Electric CooperativeOpen
2026-08-26San Antonio, Cibolo pursue data center regulations, but moratorium idea lingers
Reports that after the town hall council agreed by consensus to hold a joint meeting to draft UDC amendments; that neither a moratorium nor a ban was ruled out; and that the city's attorneys said either carries some litigation risk.
Focus On San AntonioRead
2026-08-13Cibolo residents encouraged to attend public meeting on proposed data center
Previews the August 17 town hall; describes Councilwoman Patterson sharing the staff presentation and a Green Valley SUD presentation with residents.
Seguin TodayRead
2026-07-28Can Texas communities such as Cibolo find ways to regulate data centers?
Reports that Councilmember Katie Cunningham said council was told in 2025 that utilities lacked capacity for a data center, and that she learned of the approved site plan in early July 2026. Says Legacy's site could expand to 150 MW and is planned to go online in late 2027.
Focus On San AntonioRead
2026-07-28Texas law shields San Antonio-area data center water usage from public records requests
Covers the Cibolo site, the resident petition and the councilmember's statement; says the city manager had not responded to its questions.
KSATRead
2026-06-25Polsinelli Represents Legacy Investing in Acquisition of 50MW Texas Data Center Development Site
Law firm announcement that Legacy Investing acquired 'a development site outside San Antonio, Texas' for 'a 50-megawatt data center campus.' Seller, price and closing date are not stated.
PolsinelliOpen
2026-06-11Legacy Marion data center (San Antonio Business Journal)
Not opened (subscriber site). KSAT cites it for the 243,000 sq ft figure; date taken from the URL.
San Antonio Business JournalRead
2026-06-01Legacy Investing Plans 50MW Data Center Near San Antonio, Texas
Reports the company's announcement: 39 acres, more than 100,000 sq ft of data hall in about 243,000 sq ft, 50 MW expandable to 150 MW, operational in the fourth quarter of 2027. Quotes the karting complex's January statement that 'the developer required an immediate closure as part of the sale.'
BaxtelRead
Legacy Investing eyes 50MW data center outside San Antonio, Texas
Not opened (HTTP 403 to automated requests). Listed from search results.
DataCenterDynamicsRead
Growth sparks power lines plan in county
2020 story on GVEC's plan for a substation off Bolton Road west of Santa Clara Road and a 138 kV line (the Santa Clara Transmission Line project). Background only: it predates the data center and does not mention it. The city staff deck refers to 'the substation on Bolton Road'; that this is the same substation is an inference.
Seguin Gazette, republished by Seguin EDCRead
Citizen Portal article on Cibolo council and data center permits
Not opened (HTTP 403 to automated requests). Listed from search results.
Citizen PortalRead

Timeline

  1. Cibolo City Council. Scheduled public hearing on adoption of the 2027 Unified Development Code. Source
  2. Cibolo City Council, Planning and Zoning Commission, EDC and UDC Advisory Committee. Joint workshop on developing data center regulations and procedures for unlisted land uses. No minutes posted as of 2026-11-27. Source
  3. Texas Commission on Environmental Quality. Construction stormwater coverage TXR1564ZS issued to Sitespan, LLC for the site. A San Antonio Report story published by Texas Public Radio on October 22 quotes a TCEQ spokesperson as saying on October 21 that permits issued after the governor's directive had been suspended; the TCEQ registry still showed this coverage as Active on 2026-11-27.
  4. Cibolo City Council. Item 9.B: update on data center UDC amendments; council discussed dates for the joint meeting.
  5. Governor of Texas. Governor Abbott directed TCEQ to halt permits sought by data centers until ERCOT completes an audit (reported by Texas Public Radio). Source
  6. City of Cibolo. A city permit for 'Legacy San Antonio Data Center - 1000 Bolton' was issued, per the October 2026 Economic Development report. The August report describes a commercial concrete permit for Building Phase 1.
  7. Texas Comptroller. 'Legacy Data Center SAT-1' registered as a qualifying data center, with 1000 Bolton Rd Owner, LLC as owner, occupant and operator. Source
  8. Cibolo City Council. Hearing on the UDC Sec. 4.4.7 amendment; council voted 6-1 to send it to the EDC for review before reconsidering.
  9. Texas Commission on Environmental Quality. Construction stormwater general permit coverage TXR1501ZI in effect for Legacy Investing at 1000 Bolton Road.
  10. City of Cibolo. Revised site plan PZ-2026-3-SP stamped approved, three days after the City Engineer's conformance letter. The city's August report gives August 28.
  11. Cibolo City Council. Data Center Town Hall at Steele High School, then a special meeting. The mayor asked for a joint meeting of Council, Planning and Zoning, the EDC and the UDC committee to work on regulations. No vote on regulations. Source
  12. Cibolo Planning and Zoning Commission. Recommended an amendment to UDC Sec. 4.4.7 on unlisted uses (7-0). Held a hearing on UDC amendments regarding data centers; no one spoke and no recommendation was made (minutes: tabled; city hearings page: no motion made).
  13. Cibolo City Council. Item 16.F: discussion of possible data center regulations, with a staff presentation on the 1000 Bolton Road approvals. Six speakers and four emails opposed or questioned the project. No vote. Source
  14. Cibolo City Council Ordinance Subcommittee. Discussed a framework for data center regulations and recommended council consider the approval process and standards for water, energy, pollution and noise (per the July 28 staff report).
  15. Cibolo City Council. Five speakers, including a Guadalupe County commissioner, opposed a data center during public comment. The mayor said a town hall would be scheduled.
  16. A resident petition to relocate the data center was created on Change.org; it showed 4,083 signatures on 2026-11-27. Source
  17. Polsinelli. Law firm announced it represented Legacy Investing in acquiring the development site. Source
  18. Legacy Investing. Company announced a 50 MW data center at 1000 Bolton Road, expandable to 150 MW, to be operational in the fourth quarter of 2027 (reported by Baxtel). Source
  19. City of Cibolo. Application PZ-2026-3-SP received to revise the approved plan to a single 242,640 sq ft building (date per the city staff report).
  20. Texas Secretary of State. 1000 Bolton Rd Owner, LLC registered in Texas. This is the entity later registered with the Comptroller for 'Legacy Data Center SAT-1'.
  21. City of Cibolo Planning Department. Site plan PZ-2026-2-SP approved administratively, with no public hearing or council vote. The city signature on the plan is dated April 28; staff reports give April 29.
  22. Guadalupe Valley Electric Cooperative. Letter to the city stating GVEC has adequate capacity to serve the project and that binding contracts with the developer are in place.
  23. City of Cibolo. Site plan application PZ-2026-2-SP received for two 268,600 sq ft buildings (date per the city staff report).
  24. Green Valley Special Utility District. Transmitted water and wastewater feasibility studies for 1000 Bolton Road to the applicant's engineer.
  25. Texas Secretary of State. 1000 Bolton Road, LLC registered in Texas (date per the Comptroller's franchise tax record). The first site plan names '1000 Bolton Rd, LLC' at the same San Antonio address as owner/developer; that the two are the same company is an inference from the name and address.
  26. City of Cibolo. The January 2025 Economic Development report listed 'Data Center @ 1000 Bolton Rd (Pre-Application)'. The entry stayed on the monthly reports through February 2026.
  27. Cibolo City Council. Ordinance 1173 zoned 39.14 acres Light Industrial (I-1) with a conditional use permit for a commercial go-kart complex.
  28. Cibolo City Council. Ordinance 1172 annexed about 48 acres north of Bolton Road and east of Stolte Road at the owner's request.
  29. Cibolo Planning and Zoning Commission. Public hearing on rezoning the tract from Agricultural to Light Industrial (I-1) with a conditional use permit for a go-kart complex; the commission recommended approval. Source

See an error or have a document that belongs here? Tell us.