A proposed data center park on San Antonio's South Side that industry trackers attribute to Denver-based Tract. Trackers give the size as 339 acres. The only public record found is an appraisal account for 330.40 acres on Mauermann Road, new for 2026, owned by TXLCO San Antonio LLC at the same Denver address as Tract's management company. No announcement, permit or city filing was found, and a 720 MW figure that appears on directory sites has no public source.
Where this stands and what you can do
No final local approval is on record. This is when residents have the most say: hearings and votes on annexation, zoning, tax breaks and utility agreements are still ahead.
Ask for conditions before any vote. A city or county that is asked for annexation, zoning, utilities or a tax break can attach terms: a water cap with annual reporting, noise limits, setbacks from homes, limits on generator testing hours. Ask for them in writing and ask that the draft agreement be posted before the vote.
A letter you can copy: ask for conditions before a vote
Send to: Mayor and council members. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.
Subject: Applewhite Technology Park - conditions before any vote
Dear Mayor and Council Members,
I live in [neighborhood / street] and I am writing about Applewhite Technology Park (Tract).
I am not asking you to turn away investment. I am asking that no annexation, zoning change, utility agreement or tax abatement for this project be approved until the following are written into the ordinance or the agreement itself:
1. Water: a cap on annual water use, stated in acre-feet, with a yearly public report of actual use.
2. Noise: a limit measured at the property line, and set hours for testing backup generators.
3. Distance: a minimum setback and a buffer between the buildings, the generators and the nearest homes.
4. Power: disclosure of any on-site power plant or generators, and the air permits they will need.
5. Money: any tax abatement tied to a minimum investment, a jobs and wage floor, and a clawback if those are missed.
6. Transparency: the draft agreement posted publicly at least [14] days before the vote.
Please tell me which of these the current draft includes, and when the public will be able to read it.
Thank you,
[Name]
[Address]
[Phone or email]
Speak or write on the tax abatement. A tax abatement is a choice, not an obligation. Ask the body considering one to deny it, shorten it, or tie it to jobs, wages and a clawback if promises are missed.
Send to: The body considering the abatement (city council or commissioners court). Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.
Subject: Tax abatement for Applewhite Technology Park
Dear [Mayor and Council Members / Judge and Commissioners],
I am writing about the tax abatement requested for Applewhite Technology Park (Tract).
A tax abatement is your decision to make; state law does not require one. Before you vote, I ask that you:
1. State publicly the percentage, the number of years, and the dollar value of the taxes that would be forgiven.
2. Compare the request with what other Texas cities and counties have granted for similar projects.
3. Require a minimum investment, a minimum number of full-time jobs at a stated wage, and repayment if those terms are not met.
4. Require an annual compliance report, posted publicly.
5. Explain what San Antonio and Bexar County receive in return, and when.
If these terms cannot be met, I ask that you vote no.
Thank you,
[Name]
[Address]
Comment on state permits. Backup generators and on-site power plants need air authorizations from the state environmental agency. Some types take public comment; all can be the subject of a complaint.
Ask the state for rules that apply everywhere. Outside city limits, Texas counties have little power over what gets built. Changing that takes the Legislature.
A letter you can copy: write to your state senator and representative
Send to: Your Texas state senator and state representative. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.
Subject: Data center siting and reporting standards - Bexar County
Dear [Senator / Representative] [Name],
I am your constituent in Bexar County, where Applewhite Technology Park (Tract) is [proposed / being built / operating] near homes.
I support data centers being built in Texas. My concern is where and how fast. Outside city limits, counties have almost no say, and neighbors learn the terms after the vote. I ask that you support legislation that would:
1. Give counties authority to set reasonable siting standards for large data centers: setbacks from homes and schools, noise limits, and limits on on-site power generation near neighborhoods.
2. Require data centers above a set size to report their water and electricity use each year, publicly.
3. Require that tax abatement and development agreements with data centers be posted before the vote, not after.
4. Require air permits and pollution controls to be in place before on-site turbines and generators run.
Please tell me your position on these, and whether a bill addressing them is filed or planned.
Thank you,
[Name]
[Address - so your office can confirm I am a constituent]
None found for TXLCO or Tract. Legistar shows the surrounding Neal Road area south of Mauermann Road was the subject of a 2017 annexation proceeding, before this project.
Industry tracker page: 339 acres of industrial-zoned land near Toyota and Texas A&M-San Antonio, classed as a land bank; utility CPS Energy; no power figure.
The listing has been withdrawn: the page says an editorial review pulled the record while its sourcing is re-checked. Search results had shown it as proposed at 720 MW.
Directory page from search results (it returned an error to a plain request). Search snippets show 720 MW and an Old Applewhite Road, Poteet address; neither is supported by a public record found here.
The county appraisal district page for each parcel: owner, value, deed history.
Date
Document
From
Link
Bexar CAD property 1447528
Mauermann Rd (spelled Mauemann on the record). CB 4005, P-21A, Abstract 15; 330.40 acres; owner TXLCO San Antonio LLC, 3200 E Cherry Creek South Dr, Suite 700, Denver; zoning MI-1 and MI-1 S; no improvements. First listed for 2026, at $6,086,050. The account is a new parcel (P-21A) beside the remaining P-21 tract.
A Lytle-area parcel owned by TXLCO Bexar County LLC, care of Tract Management Company LP at the same Denver address, which is the basis for linking the TXLCO name to Tract.