Counties /
Data centers in Bexar County
23 documented facilities in or near Lytle, San Antonio.
- 3823 Wiseman Blvd (SN4)
A single data center building beside Microsoft's original Rogers Road site, built under a 2013 city incentive agreement. The appraisal district lists the building as built in 2014 with a 2016 addition; the tracker Baxtel says it opened in 2015. The city agreed to reimburse at least 40 percent of the city property taxes on the new investment for 15 years in return for $250 million of investment and 20 jobs. The Bexar Appraisal District lists 277,745 square feet and a 2026 improvement value of $110 million; its land account, covering Lots 4 and 5, is 25.54 acres.
- ALE060 / COPT Potranco
A 109,000-square-foot data center on a 30.6-acre lot owned by COPT San Antonio LP and occupied by Amazon Data Services, built in 2021 under the project name AWS Rockfish. In 2026 COPT registered a second, two-story building of about 142,000 square feet on the same lot for a single data center tenant, with construction scheduled from October 2026.
- ALE061 "Bitter Blue"
A 109,000-square-foot Amazon data center on a 48.9-acre lot on Donop Road on the far Southeast Side, built in 2021 under the project name AWS Rockfish. In March 2026 Amazon registered a second, two-story building of 119,407 square feet (Building B, $65 million) with construction scheduled from December 2026; TCEQ stormwater permits issued in 2026 call the new work AWS ALE 64.
- ALE062 "Lavender Hill"
A 109,000-square-foot Amazon data center on 37.5 acres on State Highway 211 in far west Bexar County, built in 2021 under the project name AWS Rockfish. In March 2026 Amazon registered a second, two-story building of 93,145 square feet (Building B, $65 million) with construction scheduled from November 2026 to September 2028.
- Applewhite Technology ParkProposed · decisions still open
A proposed data center park on San Antonio's South Side that industry trackers attribute to Denver-based Tract. Trackers give the size as 339 acres. The only public record found is an appraisal account for 330.40 acres on Mauermann Road, new for 2026, owned by TXLCO San Antonio LLC at the same Denver address as Tract's management company. No announcement, permit or city filing was found, and a 720 MW figure that appears on directory sites has no public source.
- Black Mountain Power San AntonioProposed · decisions still open
About 431 acres of undeveloped land on State Highway 16 at Lone Star Pass, owned by Fort Worth-based Black Mountain Power LLC, which describes its business as preparing powered land for large data centers. Trackers list the site as land banked or planned. No building, zoning case, air permit or power figure was found in public records.
- I-35 Technology ParkApproved · not yet built
A 344.5-acre data center and business park site on the Bexar County side of Lytle, developed by Denver-based Tract. Lytle approved a development agreement and a utility service agreement; no tax abatement has been requested on the record.
- Omicron Drive campus (SAT5, SAT6)
Two two-story CyrusOne data centers on 22 acres at Texas Research Park, outside the San Antonio city limits. State filings estimated completion of the first building (SAT5) in July 2020 and of the first two data halls in the second (SAT6) in January 2025; the tracker Baxtel gives 2020 and January 2025, and the San Antonio Report described two operating facilities on the campus in October 2026. CyrusOne lists 33 MW of IT capacity for the two buildings. The appraisal district shows the neighboring 9.96-acre lot at 14785 Omicron Dr passed from a CyrusOne entity to the City of San Antonio by deed dated 15 January 2026; state stormwater records and the San Antonio Report describe a substation there. A tracker, Baxtel, says the lot was once planned for a third building, SAT7, that was cancelled before construction; no record opened confirms that plan or a cancellation. The state lists one air quality complaint, about smoke, for the regulated entity covering this campus and SAT8/SAT9: received in July 2025 and closed that September after a compliance investigation, with no notice of violation or enforcement issued and no findings published.
- Rogers Road SN7
A data center building that the tracker Baxtel and the San Antonio Report say Stream Data Centers first developed. The appraisal district shows it passed from Westover RTF 2 LP to Chevron in July 2011 and from Chevron to Microsoft by deed dated 31 October 2017, for a reported $80 million. Microsoft registered three data halls (colos) with the state in 2019, with estimated completion dates of December 2019 and September 2021; the appraisal district lists 93,100 square feet built in 2020. The Bexar Appraisal District lists 296,874 square feet on 33.44 acres and a 2026 market value of $125 million.
- San Antonio 2
A QTS data center campus on about 32 acres at Potranco and Ingram roads, inside the San Antonio city limits. The first building, a three-story, 338,721-square-foot data center registered for 45 MW of critical power, was scheduled for completion in April 2022 (the tracker Baxtel says it opened that year); QTS describes the campus as 90 MW or more. A second building is planned, and a 7.6-acre adjoining lot held by a QTS infrastructure entity has a small structure built in 2024.
- San Antonio IIIProposed · decisions still open
Three vacant lots totaling 48.39 acres on Omicron Drive at Texas Research Park, owned by QTS San Antonio III LLC. The San Antonio Planning Commission approved the three-lot plat, the Omicron Subdivision, in May 2023. No building registration or environmental permit was found, and QTS has not announced a project here; the tracker Baxtel lists the site as planned for 2028.
- San Antonio III (SATB campus)
A 135-acre campus at West Military Drive and Loop 1604 that Stream says will hold up to five 40 MW buildings, 200 MW and 1.5 million square feet at full build. The appraisal district lists the first building, SATB1 (304,232 sq ft), as built; no public record found states when it entered service. The state data center registry lists Microsoft as its occupant. Stream said the campus includes an on-site 334 MW CPS Energy substation.
- SAT CampusProposed · decisions still open
A planned five-building CloudHQ data center campus on 123.4 acres at Texas Research Park, the former University of Texas Health Science Center laboratory site, outside the San Antonio city limits. The UT System sold the land in May 2023. CloudHQ advertises 3,023,300 square feet and 600 MW of critical IT load with multiple on-site substations; no building registration or environmental permit was found as of November 2026.
- SAT10/SAT11Proposed · decisions still open
A vacant 25.69-acre tract on Lambda Drive at Texas Research Park owned by a CyrusOne entity, outside the San Antonio city limits. The appraisal district shows the entity bought it from the Texas Research & Technology Foundation by deed dated 9 September 2023. The tracker Baxtel says it is for two data centers, SAT10 and SAT11, and that CyrusOne agreed to start construction within 36 months; no record opened confirms those terms. No building registration, Planning Commission plat item or environmental permit for the tract was found as of November 2026.
- SAT8/SAT9Under construction · local approvals done
A two-story CyrusOne data center on 10 acres at Texas Research Park, south of the company's SAT5 and SAT6 buildings and outside the San Antonio city limits. CyrusOne calls its two halves SAT8 and SAT9 and describes 276,000 square feet and 36 MW. Plans were registered with the state in November 2023, the San Antonio Planning Commission approved the one-lot plat in June 2024 and the company announced the groundbreaking that summer; the appraisal district lists two 134,388-square-foot improvements (year built 2024), the state construction filing is still open with an estimated completion of December 2025, and no tenant fit-out filing was found as of November 2026.
- Sentry Gateway Data Center
A data center on a 28-acre lot owned by COPT San Antonio II, L.P., which state construction filings call EX West Green Data Center and TCEQ registers as Sentry Gateway Data Center with Microsoft Corporation as owner and operator. The site appears to be in operation: the appraisal district lists data center modules built 2019-2022, the state construction filings for both phases are closed, and TCEQ lists Microsoft as owner and operator with active air and tank registrations (air registration last revised June 2025). Microsoft also owns two adjoining lots (properties 1142335 and 1177240); the appraisal district dropped the improvement value on one of them from $17.5 million in 2025 to $0 in 2026, and neither shows a building in the 2026 appraisal records.
- Texas Research Park campus (SAT09-13, SAT40, SAT46)
Microsoft's campus in Texas Research Park, on land bought in December 2015 and built out since 2016. The Bexar Appraisal District lists 115.6 acres and about 1 million square feet in Bexar County; the 2015 purchase was reported as 158 acres, and a tracker (Baxtel) puts a further 55.5 acres in Medina County. The tracker Cleanview lists 409 MW of operating capacity for the campus; no utility, permit or company figure was found.
- TX1 campus (TX11, TX12)Under construction · local approvals done
Two data center buildings on about 58 acres on Omicron Drive at Texas Research Park. TX11 (32 MW of IT capacity, per its state construction filing) is built and TX12 (up to 96 MW, per its filing) is under construction. The state registry listed Microsoft as occupant of TX11 from 2024-03-06 until that registration ended 2025-11-04; a new registration effective 2025-11-05 lists Oracle America Cloud Services as occupant of TX11-12. VoltaGrid holds a state air registration for an on-site natural gas plant of 80 engines, of which 20 were built and ten running in January 2026 according to a TCEQ report cited in a notice of intent to sue; Vantage has registered 86 diesel backup generators. Public Citizen and the Sierra Club, represented by the Environmental Integrity Project, sued over its air permits in September 2026, and a TCEQ hearing on the campus's federal operating permit was cancelled in August 2026 and not rescheduled as of this writing.
- TX2 campus (TX21, TX22)Under construction · local approvals done
Two data center buildings on 31 acres at Rogers Road and State Highway 151 in Westover Hills. TX21, a three-story building, is at least partly operating and TX22 is under construction; the state registry lists Oracle America Cloud Services as occupant since 2025-11-05. Vantage has registered 65 diesel generators there, and VoltaGrid holds a state air registration for an on-site natural gas plant of 36 engines; whether that plant has been built or started was not established in the records found. TCEQ held a hearing on its federal operating permit on 2026-05-28, and Public Citizen and the Sierra Club, represented by the Environmental Integrity Project, sued over the air permits in September 2026.
- Westover Hills campus (SAT2-SAT4)
CyrusOne's second San Antonio campus: three data center buildings on about 21.6 acres in Westover Hills, built between 2014 and 2017 next to a residential neighborhood. The state's qualifying data center registry lists Microsoft as occupant of two CyrusOne-owned entries named San Antonio Data Center II and San Antonio Data Center III; the registry gives no addresses, and they are matched to this campus by those names. The state's Chapter 312 registry lists a City of San Antonio tax abatement agreement with CyrusOne LLC signed in September 2013 and in effect from 2015 through 2020; the registry names no property, and its link to this campus is an inference from the timing of the land purchase.
- Westover Hills SN1/SN2
Microsoft's first San Antonio data center: two buildings on about 36 acres per the appraisal district (the 2007 abatement described 44 acres) at 5150 Rogers Road, approved for city incentives in January 2007 and opened in 2008 according to Data Center Knowledge. The city granted a 10-year, 100 percent property tax abatement and CPS Energy was asked for up to $5.2 million toward electrical infrastructure. The Bexar Appraisal District lists 463,350 square feet and a 2026 market value of $112 million.
- Westover Link SAT15-17
A planned three-building campus at State Highway 151 and Westover Link, on about 71 acres by the county parcel map (the appraisal district's land lines total about 76 acres). SAT15 was registered with the state in 2022 and holds active air permits. No record opened states that any building is in service: SAT15's state filing shows its inspection complete and the tracker Baxtel says its first colos came online in 2025. SAT16 and SAT17 were registered in 2024 with estimated completion dates of December 2025 and December 2027, and nothing opened shows either complete. The Bexar Appraisal District lists one 256,800-square-foot building and a 2026 market value of $65 million.
- Wiseman Blvd SAT14
Two data center buildings on about 33.6 acres in a subdivision platted as Valero Data Expansion II; the tracker Baxtel says Microsoft bought the land from Valero in late 2020. No record opened states when the buildings entered service: the appraisal district lists both as built in 2022, the state filings for the fit-out phases show inspections complete with an estimated completion of 31 March 2026, and Baxtel says the first colos came online in 2024. The city's staff and Development Services director denied Microsoft's request to remove more trees than the tree ordinance allows; the Planning Commission overturned that 6-1 and the City Council affirmed it 8-3 in January 2022, allowing the removal of 2,157 of the site's 2,226 significant and heritage trees by the city memo's count (2,642 trees in all, according to the San Antonio Report). The Bexar Appraisal District lists 260,384 square feet and a 2026 market value of $65 million.